Southern Thailand rail expansion gets 106.8 billion baht backing
The second phase will add 504 kilometres of double-track railway, with tenders targeted for 2027. Two bridges in Songkhla and Krabi are also due to start construction.

Southern Thailand is set for a 106.8 billion baht railway expansion, with the State Railway of Thailand preparing tenders for three new double-track sections. Deputy Transport Minister Sanphet Boonyamanee said on November 7 that tenders and contract signings are targeted for 2027, and the full second phase is scheduled for completion by 2033.
The planned 504 kilometres of track will extend the existing line south from Chumphon to Surat Thani, then to Hat Yai Junction and Padang Besar. The first 420-kilometre section, between Nakhon Pathom and Chumphon, has operated since 2024. The new sections are intended to improve regional connections and reduce transport costs, although construction will take several years.
For residents, businesses and visitors, the rail plan is part of a wider push to improve transport links across the South. The ministry says it is also working on two bridges expected to make journeys in Songkhla and Krabi shorter and easier.
Three sections, with work planned from 2026
The Cabinet approved the railway sections at a meeting in Songkhla on September 1. The Chumphon–Surat Thani section will cover about 168 kilometres, with implementation planned for fiscal years 2026 to 2032. The 291-kilometre Surat Thani–Hat Yai Junction section is also planned for implementation from fiscal 2026 to 2033.
The final section, from Hat Yai Junction to Padang Besar, will cover about 45 kilometres. Its planned implementation period is fiscal 2026 to 2031. The ministry says it will address land constraints, review designs where needed and include measures to reduce flood risks. The exact dates for construction to start have not been announced.
Bridge construction due to start in November
The Department of Rural Roads plans to issue notices to begin work on November 14 on a bridge across Songkhla Lake, linking Songkhla and Phatthalung, and a bridge connecting Koh Lanta in Krabi. Contracts were signed on August 31. Both projects are expected to take three years, with completion planned for 2029.
The Songkhla Lake bridge has an estimated budget of 4.6 billion baht and is expected to cut the journey between the provinces by about 80 kilometres, reducing travel time from nearly two hours to 15–30 minutes. The 1.78 billion baht Koh Lanta bridge is intended to reduce reliance on vehicle ferries and improve access for travel, goods, medical services and emergency response.
This report draws on information from Thaiger.